HomeMy WebLinkAboutDavid J. Powers & AssociatesAGREEMENT
THIS AGREEMENT is made and entered into on the 17th day of July, 2020 by and
between the TOWN OF LOS ALTOS HILLS (hereinafter referred to as "TOWN") and
David J. Powers & Associates, Inc. (hereinafter referred to as "CONTRACTOR"). In
consideration of their mutual covenants, the parties hereto agree as follows:
1. CONTRACTOR. Shall provide or furnish the following specified services and/or
materials:
Complete environmental review consulting services in
compliance with the California Environmental Quality Act
(CEQA) for the off-road pathway segment located between La
Paloma Road and Robleda Road in the Los Altos Hills.
2. EXHIBITS. The following attached exhibits are hereby incorporated into and made a
part of this Agreement:
Proposal from CONTRACTOR dated July 10, 2020
3. TERMS. The services and/or materials furnished under this Agreement shall
commence July 17, 2020 and shall be completed by'July 17, 2021, unless terminated
pursuant to Section 5(f).
4. COMPENSATION. For the full performance of this Agreement:
a. TOWN shall pay CONTRACTOR an amount not to exceed thirty seven thousand
dollars and zero cents ($37,000.00) within thirty (30) days following receipt of
invoice and completion/delivery of services/goods as detailed in Sections 1, 2, and
3 of this Agreement and only upon satisfactory delivery/completion of
goods/services in a manner consistent with professional/industry standards for the
area in which CONTRACTOR operates. TOWN is not responsible for paying for
any work done by CONTRACTOR or any subcontractor above and beyond the not
to exceed amount.
b. Town shall not reimburse for any of CONTRACTOR's costs or expenses to deliver
any services/goods. Town shall not be responsible for any interest or late charges
on any payments from Town to CONTRACTOR.
c. CONTRACTOR is responsible for monitoring its own forces/employees/agents/
subcontractors to ensure delivery of goods/services within the terms of this
Agreement. TOWN will not accept or compensate CONTRACTOR for incomplete
goods/services.
Town of Los Altos Hills Page 1 of 4
Short form
Updated 4/23/10
5. GENERAL TERMS AND CONDITIONS.
a. HOLD HARMLESS. CONTRACTOR agrees to indemnify, defend and hold
harmless the TOWN, its officers, agents and employees from any and all demands,
claims or liability of personal injury (including death) and property damage of any
nature, caused by or arising out of the performance of CONTRACTOR under this
Agreement. With regard to CONTRACTOR'S work product, CONTRACTOR
agrees to indemnify, defend and hold harmless the TOWN, its officers, agents and
employees from any and all demands, claims or liability of any nature to the extent
caused by the negligent performance of CONTRACTOR under this Agreement.
b. INSURANCE. CONTRACTOR shall file with the TOWN a certificate of insurance
before commencing any services under this Agreement as follows:
WORKERS COMPENSATION INSURANCE: Minimum statutory limits.
ii. COMMERCIAL GENERAL LIABILITY AND PROPERTY DAMAGE
INSURANCE: General Liability and Property Damage Combined.
$1,000,000.00 per occurrence including comprehensive form, personal
injury, broad form personal damage, contractual and
premises/operation, all on an occurrence basis. If an aggregate limit
exists, it shall apply separately or be no less than two (2) times the
occurrence limit.
iii. AUTOMOBILE INSURANCE: $1,000,000.00 per occurrence.
iv. ERRORS AND OMISSIONS INSURANCE: $1,000,000.00 aggregate.
v. NOTICE OF CANCELLATION: The City requires 30 days written notice
of cancellation. Additionally, the notice statement on the certificate
should not include the wording "endeavor to" or "but failure to mail such
notice shall impose no obligation or liability of any kind upon the
company, its agents or representatives."
vi. CERTIFICATE OF INSURANCE: Prior to commencement of services,
evidence of insurance coverage must be shown by a properly executed
certificate of insurance and it shall name "The Town of Los Altos Hills,
its elective and appointed officers, employees, and volunteers" as
additional insureds.
vii. To prevent delay and ensure compliance with this Agreement, the
insurance certificates and endorsements must be submitted to:
Town of Los Altos Hills
26379 Fremont Road
Los Altos Hills, CA 94022
Town of Los Altos Hills Page 2 of 4
Short form
Updated 4/23/10
c. NON-DISCRIMINATION. No discrimination shall be made in the employment of
persons under this Agreement because of the race, color, national origin, age,
ancestry, religion or sex of such person.
d. INTEREST OF CONTRACTOR. It is understood and agreed that this Agreement
is not a contract of employment and does not create an employer-employee
relationship between the TOWN and CONTRACTOR. At all times
CONTRACTOR shall be an independent contractor and CONTRACTOR is not
authorized to bind the TOWN to any contracts or other obligations without the
express written consent of the TOWN. In executing this Agreement,
CONTRACTOR certifies that no one who has or will have any financial interest
under this Agreement is an officer or employee of TOWN.
e. CHANGES. This Agreement shall not be assigned or transferred without advance
written consent of the TOWN. No changes or variations of any kind are authorized
without the written consent of the City Manager. This Agreement may only be
amended by a written instrument signed by both parties.
f. TERMINATION. This Agreement may be terminated by TOWN upon seven (7)
days written notice to CONTRACTOR. Monies owed for work satisfactorily
completed shall be paid to CONTRACTOR within 14 days of termination.
g. RECORDS. All reports, data, maps, models, charts, studies, surveys,
calculations, photographs, memoranda, plans, studies, specifications, records,
files, or any other documents or materials, in electronic or any other form, that are
prepared or obtained pursuant to this Agreement and that relate to the matters
covered hereunder shall be the property of the TOWN. CONTRACTOR hereby
agrees to deliver those documents to the TOWN at any time upon demand of the
TOWN. It is understood and agreed that the documents and other materials,
including but not limited to those described above, prepared pursuant to this
Agreement are prepared specifically for the TOWN and are not necessarily
suitable for any future or other use. Failure by CONTRACTOR to deliver these
documents to the TOWN within a reasonable time period or as specified by the
TOWN shall be a material breach of this Agreement. TOWN and CONTRACTOR
agree that until final approval by TOWN, all data, plans, specifications, reports and
other documents are preliminary drafts not kept by the TOWN in the ordinary
course of business and will not be disclosed to third parties without prior written
consent of both parties. All work products submitted to the TOWN pursuant to this
Agreement shall be deemed a "work for hire." Upon submission of any work for
hire pursuant to this Agreement, and acceptance by the TOWN as complete, non-
exclusive title to copyright of said work for hire shall transfer to the TOWN. The
compensation recited in Section 4 shall be deemed to be sufficient consideration
for said transfer of copyright. CONTRACTOR retains the right to use any project
records, documents and materials for marketing of their professional services.
Town of Los Altos Hills Page 3 of 4
Short form
Updated 4/23/10
h. ENTIRE AGREEMENT. This Agreement represents the entire agreement
between the Parties. Any ambiguities or disputed terms between this Agreement
and any attached Exhibits shall be interpreted according to the language in this
Agreement and not the Exhibits.
6. INVOICING. Send all invoices to the contract coordinator at the address below.
This Agreement shall become effective upon its approval and execution by TOWN. In
witness whereof, the parties have executed this Agreement the day and year first written
above.
CONTRACT COORDINATOR and
representative for TOWN:
Zachary Dahl
Planning Director
Town of Los Altos Hills
26379 Fremont Road
Los Altos Hills, CA 94022
CONTRACTOR:
By: July 29, 2020
Signature Date
Akoni Danielsen, President
Print name, Title
TOWN OF LOS ALTOS HILLS:
By: ��
arl-Gahriil -Gitynager Date
z 4e'4 D" t
Town of Los Altos Hills Page 4 of 4
Short form
Updated 4/23/10
� � & ASSOCIATES, INC.
July 10, 2020
Zachary Dahl
Planning Director
Town of Los Altos Hills Planning Department
26379 Fremont Road
Los Altos Hills, CA 94022
Sent via email to: zdahl@losaltoshills.ca.gov
RE: SCOPE OF WORK - ENVIRONMENTAL REVIEW SERVICES FOR THE PROPOSED LA PALOMA
ROAD TO ROBLEDA ROAD OFF-ROAD PATHWAY
Dear Mr. Dahl,
David J. Powers & Associates (DJP&A) is pleased to provide you with this scope of work to complete
environmental review consulting services in compliance with the California Environmental Quality
Act (CEQA) for the proposed project located between La Paloma Road and Robleda Road in the Los
Altos Hills township. This scope is based upon a review of the information provided by the Town, as
well as DJP&A's experience with projects of similar size and purpose.
It is our understanding that the project would construct a pedestrian pathway connecting the
existing pathway at 13310 La Paloma Road to the existing pathway at 12940 Atherton Court.
Pathway improvements would include pedestrian bridges, a stairway linking the proposed pathway
and the Robleda Road pathway, and several retaining walls. The primary environmental concerns
include the presence of biological resources (mixed -oak woodland and riparian habitat) and
potential landslide hazards and cultural resources along the proposed trail alignment.
With our current understanding of the project and its potential environmental impacts, DJP&A
proposes to prepare an Initial Study to determine if the project would have a significant effect on
the environment. Based upon our understanding of the site, surrounding context, and scale of the
project, it appears all project impacts can be mitigated to acceptable levels allowing for adoption of
a Mitigated Negative Declaration. In the event a significant unavoidable impact is identified for the
project, an Environmental Impact Report could be prepared under an amended scope.
Environmental Consultants and Planners
1871 The Alameda • Suite 200 • San Josh, CA 95126 • Tel: 408-248-9641 • www.davidjpowers.com
La Paloma Road to Robleda Road Off -Road Pathway
July 10, 2020
Please do not hesitate to contact me if you have any questions regarding this proposed Scope of
Work or if there is any additional information you may need. We look forward to working with you
on this project.
Sincerely,
�P_V,A QAY%. Lo�kas_�
Demetri Loukas
Principal Project Manager
Attachments: Scope of Work
Charge Rate Schedule
Environmental Consultants and Planners
1871 The Alameda • Suite 200 • San Josh, CA 95126 • Tel: 408-248-9641 • www.davidjpowers.com
+
a - ASSOCIATES 1N'C,
La Paloma Road to Robleda Road Off -Road Pathway
Initial Study — Mitigated Negative Declaration
July 2020
Primary Contact
The primary David J. Powers & Associates, Inc. (DJP&A) contact information is provided below.
Demetri Loukas
Direct: (408) 454-3422
Email: dloukas@davidipowers.com
Project Understanding
The project proposes to construct a compacted dirt pathway approximately three feet wide and 960
feet in length. The proposed pathway would connect the existing pathway at 13310 La Paloma Road
to the existing pathway at 12940 Atherton Court. Pathway improvements would include pedestrian
bridges, a stairway linking the proposed pathway and the Robleda Road pathway, and several
retaining walls. Some grading and native brush and plant removal would be required for pathway
leveling and the installation of the pathway improvements, but tree removal would not be
necessary.
The project site itself is located within an existing 20 -foot wide pathway and equestrian easement
surrounded by low-density single-family residences and a small undeveloped property owned by
the Purissima Water District. This easement has a Residential (R) and Open Space Conservation
Area (OSCA) land use designation and is zoned for Residential -Agricultural (R -A) use. The project site
is also within a riparian corridor that is adjacent to a tributary drainage channel of Adobe Creek.
Scope of Services
David J. Powers & Associates, Inc. (DJP&A) will prepare an Initial Study for the La Paloma Road to
Robledo Road Off -Road Pathway project. Our scope includes preparation of the Initial Study,
preparation of a draft Mitigated Negative Declaration (MND), preparation of a draft Mitigation
Monitoring and Reporting Program (MMRP), attendance at meetings and hearings, and project
management and contract administration. These tasks are described below.
David J. Powers & �sociat �s. Inc. Quality Envirorunentrri Revie: Naa;Ces o Difference
La Paloma Road to Robleda Road Off -Road Pathway
July 10, 2020
Preparation of the Initial Study
DJP&A will prepare an Initial Study consistent with the requirements of the California
Environmental Quality Act (CEQA) and the Town of Los Altos Hills. This scope is based on the
understanding the project would be eligible for an MND, assuming there are no significant impacts,
or mitigation measures are included in the project to reduce any impacts to a less than significant
level.
The Initial Study will include a project description, discussion of consistency with applicable plans
and policies, and a section that includes a description of existing conditions on the site, the CEQA
environmental checklist, and an explanation of project effects and mitigations, as described below.
Project Description
The Initial Study will provide a detailed description of the proposed project, including the physical
characteristics (grading, excavation, landscaping, etc.) of the development. Maps and graphics will
be provided to illustrate the text.
Consistency with Plans and Policies
A discussion of the proposed project's consistency with the Los Altos Hills General Plan, Municipal
Code, and other applicable plans and policies will be included. As required by CEQA and CEQA
Guidelines, particular attention will be given to inconsistencies, if any are identified.
Environmental Setting, CEQA Checklist, and Mitigations
The Initial Study will be divided into subsections for each environmental resource. The subsections
will be formatted to include a description of the existing environmental setting followed by the
relevant CEQA checklist section. The sources of information for determining impacts will be
identified. Mitigation measures will be identified to reduce significant impacts as appropriate.
Based upon our current understanding of the project, we anticipate the key environmental issues
for the project requiring technical and/or substantial analysis will include the following resources.
Biological Resources
There is a riparian habitat present on-site along a tributary drainage channel of Adobe Creek that is
surrounded by mixed -oak woodland habitat. As such, certain mammals, reptiles, and predatory
birds and passerines may be present, including possible candidate, sensitive, or special status
species. The Initial Study will evaluate potential impacts to biological resources based on a
biological study prepared under separate contract and provided to DJP&A. The biological study will
include an assessment of the project's consistency with the Town's General Plan policies regarding
protection of creeks and riparian corridors (Policy 1.1 through Policy 1.3), trees and plants (Policy
2.1 through 2.7), and wildlife species and habitat (Policy 3.1). The biological study will also evaluate
0_ivid J. Pe%,%fern & A.6soda Les, Inc. 2 Pllokes o Difference
La Paloma Road to Robleda Road Off -Road Pathway
July 10, 2020
the potential for the project to impact raptors or other birds during construction and identify
mitigation measures for significant biological resources impacts, as appropriate.
Cultural and Tribal Resources
Areas adjacent to waterways can be archaeologically sensitive. The Initial Study will evaluate the
project's potential to impact archeological resources based on existing information provided to
DJP&A by the Town of Los Altos Hills. Standard mitigation measures in compliance with the Town's
General Plan policies and state laws will be identified for possible cultural resource impacts.
If it is determined existing information is not sufficient to make a significance determination, this
scope includes the optional task of having an archaeological literature search and field survey
report prepared by Holman & Associates. This scope assumes the Town will initiate and complete
AB 52 tribal consultation, if necessary.
Geology and Soils
The project site is located on an undeveloped hillside within a State -identified landslide hazard
zone. The Initial Study will evaluate whether the project would result in a significant geological
impact based on existing available information (e.g., General Plan and County Geologic Hazard
Maps). The Initial Study will also discuss potential impacts to paleontological resources, based on
the program -level analysis contained in the General Plan EIR. Mitigation measures will be identified
for significant geology and soils impacts, as appropriate.
Hydrology and Water Quality
Construction activities associated with the proposed project have the potential to result in
temporary hydrology and water quality impacts. Additionally, increased pedestrian traffic as a result
of the proposed pathway could affect the water quality of Adobe Creek through erosion of the
natural surfaces, thus increasing siltation in the tributary drainage channel. The Initial Study will
qualitatively describe the impacts that could result from project construction and operation and
identify best management practices for reducing and/or avoiding hydrology and water quality
impacts. If necessary, mitigation measures will be provided to reduce significant impacts to
hydrology and water quality to a less than significant level.
Revisions and Copies
Once the project description is finalized, DJP&A will prepare the Administrative Draft Initial Study
(ADIS). DJP&A will then revise the ADIS based on comments received from the Town and submit an
electronic copy of the Screencheck version to the Town for final review and comment. DJP&A will
make any final revisions to the Screencheck Initial Study and prepare the Initial Study for public
circulation. DJP&A will provide the Town with up to five (5) hard copies of the Initial Study for public
distribution and a PDF of the document for posting on the Town's website.
David J. Powers & Associates, Inc. 3 Quolit/ Environmental Review Makes o Difference
La Paloma Road to Robleda Road Off -Road Pathway
July 10, 2020
Preparation of Draft Mitigated Negative Declaration
DJP&A will prepare a draft MND in conformance with the CEQA Guidelines and Los Altos Hills
requirements. The draft MND will describe the proposed project, present findings related to the
environmental conditions, and include a copy of the Initial Study and mitigation measures to
support the findings. The draft MND will be submitted to the Town with the Screencheck Initial
Study.
Preparation of Mitigation Monitoring and Reporting Program
In accordance with state law and CEQA Guidelines, DJP&A will draft a Mitigation Monitoring and
Reporting Program (MMRP) identifying when mitigation measures will be implemented, who will be
responsible for implementing them, and who will provide oversight. The draft MMRP will be
submitted to the Town with the Screencheck Initial Study.
Preparation of Responses to Comments
DJP&A will assist Town Staff with responses to CEQA comments received during the IS/MND public
review period. Up to 2 principal and 8 project manager hours are included in this scope to complete
this task. If substantial comments are received requiring additional time or technical analysis, this
can be completed a time and materials basis upon Town authorization.
Preparation of CEQA Notices
DJP&A will prepare the project NOI and NOD in conformance with the CEQA Guidelines and Town of
Los Altos Hills requirements. The NOI will be submitted to the Town with the Screencheck Initial
Study. The NOD will be submitted to the Town during the IS/MND public comment period.
Attendance of Meetings and Hearings
This scope of work includes DJP&A attendance at one project kick-off meeting and one public
hearing (e.g., Council hearing). DJP&A can attend additional public hearings or meetings requested
on a time and materials basis.
Project Management and Contract Administration
DJP&A will provide general Initial Study project management, contract administration, and
coordination with the Town and project team throughout the Initial Study process. The DJP&A
Project Manager will coordinate with the Town on a regular basis using email and telephone
communications.
David J. Powers & Associates Inc. 4 Q.iolity fovirommentol Review Alky,< s ci Oijf-rtncc
La Paloma Road to Robleda Road Off -Road Pathway
July 10, 2020
Estimated Schedule
DJP&A proposes the following optimum schedule to prepare the Initial Study and MND. DJP&A can
commit to maintain the schedule in the areas that are within our control. Completion of the Initial
Study and MND, as outlined in the schedule below, is based upon receipt of project information
listed on the following page in accordance with the schedule. Delays in receiving requested
information or responses by others will result in at least day -for -day delays in the overall schedule.
David J. Poyle rS SOC1 t2S, Inc 5 Quolity Envi(QI7finentol rReVlc :+l ik/lakt!5 o vii, Terence
Task
Time
Task
Duration
Elapsed
1. DJP&A receives authorization to proceed and requested project
information
---
1 day
2. DJP&A reviews provided information
1 week
1 week
3. DJP&A submits project description to Town for review/approval
1 week
1 week
4. DJP&A receives technical studies from Town and, if necessary,
Holman & Associates
6 weeks
6 weeks
5. DJP&A completes Administrative Draft Initial Study (ADIS) and
submits to Town for review
3 weeks
9 weeks
6. Town reviews ADIS and provides DJP&A comments
4 weeks
13 weeks
7. DJP&A revises ADIS and submits Screencheck Initial Study/MND,
NOI, and MMRP to Town for review
2 weeks
15 weeks
8. Town completes review of Screencheck Initial Study/MND, NO[, and
MMRP and provides DJP&A with comments
2 weeks
17 weeks
9. DJP&A finalizes, prints, and submits Initial Study/MND to Town for
public circulation
1 week
18 weeks
10. Circulation of the Initial Study/MND
4 weeks
22 weeks
11. DJP&A provides Town responses to comments received during the
public review period*
1 week
23 weeks
12. Public Hearing
TBD
TBD
Total
+/-22
weeks
* Assumes substantial comments are not received and no additional technical work is required.
David J. Poyle rS SOC1 t2S, Inc 5 Quolity Envi(QI7finentol rReVlc :+l ik/lakt!5 o vii, Terence
La Paloma Road to Robleda Road Off -Road Pathway
July 10, 2020
Project Information Required
Our scope and schedule are based on the assumption that we will receive the below project
information concurrent with the authorization to proceed.
Plans (in PDF)
❑ Project plans
Project Details
❑ Written description of the project and discretionary approvals
❑ Construction schedule
Project Technical Reports
❑ Biological Resources Report
Existing Information and Studies for Project Area
❑ Cultural Resource Studies
❑ Environmental Studies
D,ivid J. Powers Ft Assodal:es, Inc, 6 Quolitj Mokes G Difference
La Paloma Road to Robleda Road Off -Road Pathway
July 10, 2020
Cost Estimate
Based on our understanding of the project and technical reports required, the cost for preparation
of the Initial Study and MND is estimated not to exceed $32,000, or $37,175 with the optional task.
Payment will be due on a monthly basis. A breakdown of the cost estimate is provided below. Costs
will be charged on a time and materials basis, commensurate with work completed, in accordance
with the charge rate schedule outlined on the following page. If DJP&A does not need all the time
that has been budgeted, we will only bill for the time actually spent completing the work.
This scope is valid for 90 days and assumes that no issues arise that would require any additional
technical analysis or documentation. In the event additional technical analysis is required, we can
complete that work on a time and materials basis, upon your authorization. Project description
changes after our notice to proceed is received may have schedule and budget implications.
David J. Powers & Associates, Inc.
• Preparation of Initial Study, MND $31,725
• Reimbursables (travel, printing, etc.)* $275
Total: $32,000.00
Optional Task
• Preparation of Archaeological Literature and Field Survey Report by $5,175.00
Holman & Associates
Total with Optional Tasks: $37,175
* Subconsultant and reimbursable expenses include our standard 15 percent administrative fee.
David J. Powers & Associates, Inc. 7 Quolity Environmental Review Mokes a Difference
La Paloma Road to Robleda Road Off -Road Pathway
July 10, 2020
Charge Rate Schedule'
Title Hourly Rate
Senior Principal $300
Principal Project Manager $275
Senior Environmental Specialist $240
Senior Project Manager $215
Environmental Specialist $200
Biologist $190
Project Manager $190
Associate Project Manager $160
Assistant Project Manager $130
Researcher $115
Draftsperson/Graphic Artist $120
Document Processor/Quality Control $110
Administrative Manager $110
Office Support $95
Notes: Materials, outside services, and subconsultants include a 15 percent administration fee. Mileage will be charged per
the current IRS standard mileage rate at the time costs occur. Subject to revision July 1, 2020.
1 David J. Powers & Associates, Inc. provides regular, clear and accurate invoices as the work on this project
proceeds, in accordance with normal company billing procedures. The cost estimate prepared for this project does
not include special accounting or bookkeeping procedures, nor does it include preparation of extraordinary or
unique statements or invoices. If a special invoice or accounting process is requested, the service can be provided
on a time and materials basis. Any fees charged to DJP&A for Client's third -party services related to invoicing,
insurance certificate maintenance, or other administrative functions will be billed as a reimbursable expense.
David J. Powers & Associates, Inc. 8 Quality Environmental Review Makes a Different,