HomeMy WebLinkAbout76-22RESOLUTION 76-22
A RESOLUTION OF THE CITY COUNCIL OF THE TOWN OF LOS ALTOS HILLS
AUTHORIZING STAFF TO AWARD A CONTRACT FOR DESIGN SERVICES FOR
THE SUMM ERHILL PATHWAY PROJECT
WHEREAS, there is currently no continuous pathway on Summerhill Avenue from Nicole Lane
to Magdalena Avenue; and
WHEREAS, the budget adopted by the City Council for Fiscal Year 20/21 included and
appropriated funding for the Phase II of the Summerhill Avenue Pathway Project; and
WHEREAS, the Public Works Director released a Request for Proposal for design services for
the Summerhill Avenue Pathway Project Phase II, and the Public Works Director evaluated and
considered the three proposals submitted; and
WHEREAS, the Public Works Director recommends that the contract for said project be awarded
to the lowest qualified bidder, Lea & Braze Engineering, Inc., for an amount of $41,780.00.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the Town of Los Altos Hills
that:
1. The City Manager is hereby authorized and directed to execute the awarded contract to
the above-named firm on behalf of the Town of Los Altos Hills.
The above and foregoing Resolution was passed and adopted by the City Council of the Town of
Los Altos Hills at a regular meeting held on the 18th day of August 2022 by the following vote:
AYES: Tyson, Swan, Mok, Schmidt, Tankha
NOES: None
ABSTAIN: None
ABSENT: None
BY:
George K. T n, May
ATTEST:
Deborah Padovan, City Clerk