WHEREAS, the Utility Engineering Manager did duly examine and consider all bids submitted
to it for the construction of the Town Hall interior renovation project; and
WHEREAS, the Utility Engineering Manager recommends that the project be awarded to L C
Builders, Inc. in the amount of $155,000; and
WHEREAS, the Utility Engineering Manager recommends that funds of $60,000 be made
available for construction contingency; and
NOW, THEREFORE, BE IT RESOLVED by the City Council of the Town of Los Altos Hills
that;
1. The City Manager is hereby authorized to execute a contract for $155,000 to the above-
named firm on behalf of the Town of Los Altos Hills for the Town Hall Paint, Carpet, and
Finance Room Remodel project.
2. The Public Works Director is hereby authorized to approve potential contract change
orders in an amount not to exceed $60,000.
3. Approve appropriation in the amount of $26,704 from the unreserved General Fund, for a
total project cost not to exceed $215,000. The remaining amount of $188,296 will come
from the available balance of $250,000 ARPA funds allocated in the 2022-23 Operating
Budget for Town Hall Furniture and space upgrade
The above and foregoing Resolution was passed and adopted by the City Council of the Town of
Los Altos Hills at a regular meeting held on the 15th day of September 2022 by the following vote:
AYES: Tyson, Swan, Mok, Schmidt, Tankha
NOES: None
ABSTAIN: None
ABSENT: None 7
BY: - o
--�'" George Tyson, yor
ATTEST: