HomeMy WebLinkAbout72-24RESOLUTION 72-24
A RESOLUTION OF THE CITY COUNCIL OF THE
TOWN OF LOS ALTOS HILLS APPROVING THE CORPORATION YARD LOCKER
ROOM PHASE 1 CONCEPTUAL DESIGN AND DIRECTING STAFF TO MOVE
FORWARD WITH FINAL DESIGN DOCUMENTS
WHEREAS, as adopted in the Operating and Capital Budgets for FY2024-2025 and FY2025-
2026, the Corporation Yard Locker Room is a Capital Improvement Project that would add
adequate locker room space with accessible shower/restroom facilities for the maintenance staff;
and
WHEREAS, the current project budget approved for the Corporation Yard Locker Room project
is $340,000, and all the proposed scope of work for the project cannot be funded within the current
budget; and
WHEREAS, staff is proposing to bifurcate the project scope into two phase; and
WHEREAS, Phase 1 scope would include the new unisex restroom/locker room on the ground
floor and the HVAC upgrade to the building, which can be completed within the project budget;
and
WHEREAS, further evaluations and discussions are needed for the second phase of the project
during the FY2025/26 budget process due to its significant funding needs due to a fire suppression
system required by fire codes.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the Town of Los Altos Hills
that;
1. The conceptual designs for Phase 1 of the Corporation Yard Locker Room Project is
approved; and
2. Staff is directed to proceed with the final design for Phase 1 of the Corporation Yard Locker
Room and report back to Council.
The above and foregoing Resolution was passed and adopted by the City Council of the Town of
Los Altos Hills at a regular meeting held on 21" day of November 2024 by the following vote:
AYES: Mok, Schmidt, Swan, Tankha, Tyson
NOES: None
ABSTAIN: None
ABSENT: None
Resolution 72-24
By: _ J4
ok, Mayor
ATTEST:
Arika Birdsong -M' r, City Clerk
Resolution 72-24